Add a Milestone

When task start date equals task end date the task is displayed as milestone. If you create new task as described in previous section and define equal start and end date and time, it will be shown as milestone – a task with zero duration.

Zero-duration task shown as a milestone when start and end dates are equal in the Virto Gantt Chart

Or click “+Milestone” to add a milestone to the chart.

+Milestone button used to add a milestone to the Virto Gantt Chart