Installing Virto Gantt Web Part

Before you begin, you need to make sure you have access to the server and your account must have the appropriate administrative privileges to install applications.

Virto Gantt Web Part for SharePoint setup program provides links to the various installation components for the calendar.

To access Virto Gantt View Setup program download Virto.SharePoint.2019.TaskManager.zip(or Virto.SharePoint.2016.TaskManager.zip or Virto.SharePoint.2013.TaskManager.zip) file and unzip it. Run extracted Setup.exeas administrator under the farm administrator account.

The setup wizard window will appear.

Opening screen of the Virto Gantt Web Part for SharePoint setup wizard

Virto Gantt Web Part wizard performs a system check prior to the installation. All the system checks must be completed successfully in order to proceed with the installation. After the checks have completed, click “Next”.

System check step of the Virto Gantt Web Part setup wizard with all checks completed

Check “I accept the terms in the License Agreement” and click “Next”.

License Agreement step of the Virto Gantt Web Part setup wizard with the accept terms checkbox

Select the web application(s) where you want to install the product.

WarningYou must be logged in to the SharePoint server with a Site Collection Administrator account to automatically activate this feature.

Selecting the web applications where the Virto Gantt Web Part will be installed

Then click “Next”.

Installation progress step of the Virto Gantt Web Part setup wizard

Click “Close” to complete the installation.

Final step of the Virto Gantt Web Part setup wizard with the Close button to finish installation