Load
The Load page shows, for each resource and period, the hours assigned to it as a percentage of the hours it can work. Show at the start of the bar switches to rows by role.

- Weeks and Months show as many weeks (up to 12) or months (up to 6) as fit the width of the page. The arrows move the period by that many, and the button between them goes back to today.
- Only overbooked lists only the resources with a period over 100 %.
- Colors: blue below 90 %, amber from 90 to 100 %, red over 100 %. A “!” means that some hours fall on days when the resource cannot work.
- Capacity follows the resource’s calendar, or the default calendar, with the public holidays, the days off and the dates when the resource is available. The hours of an assignment are spread over its working days.
Rest the pointer on a cell to see the hours the resource can work and the hours assigned in that period, and each project and role with its hours.

Click a cell with assignments and choose Show in Projects or Show on the Gantt. The Projects list or the Gantt chart then shows only the projects where that resource is assigned in that period, inactive ones included, under a bar that names the resource and the period. On the Gantt chart, those projects and roles are opened, the resource’s assignments are outlined, and the chart scrolls to the period. The cross on the bar (Show all projects) shows all projects again.
Load by roles
With Show → Roles, the Load page has a row for each role instead of each resource. It compares the hours the projects plan for the role with the hours the resources with that role can work. Over 100 % means there are not enough people for the role.

- Planned: the planned hours of each project role, spread over its dates on the working days of the default calendar. The same role in several projects is one row.
- People can work: the hours of the resources whose role it is, by their calendars, public holidays, days off and availability.
- Roles that no resource has and no project plans in the period are not listed.
- The card of a cell names the projects that plan the role in that period, with their hours. A click on the cell shows those projects in Projects or on the Gantt chart, under a bar that names the role and the period.
Only overbooked, Weeks and Months and the arrows work the same way for roles. Your choice of rows is kept in this browser.
Months and capacity
A month adds up its days, so one overbooked week can be hidden in a month that is not overbooked. When resources have no calendar and no default calendar is set, the page asks for one: the load is counted by working hours.
Load counts only the hours assigned in projects. To see time that goes to work outside projects, such as support or operations, plan it as a project of its own with roles and assignments.